Dublin Airport - Phase 5E

Client: Dublin Airport Authority

Contract Value: €1,100,000

Design Engineers: Burkes Green

Main Contractor: Clare Civil Engineering

Description: The works at Phase 5E, Dublin Airport involved the installation of AGL lighting associated with the re-paving of the live, operational taxiways including installations on new taxiways. These works included the installation of taxiway edge and centreline lights, guidance signage, stop-bars, and wigwags. Also included was the installation of FLYCY circuits, modifications to existing MV circuits, and installation of new CCRs. This project also included the expansion of the existing blown fibre optic network serving mission critical items such as the DVORs, and air traffic control equipment.