Dublin Airport - Apron 6

Client: Dublin Airport Authority

Contract Value: €930,000

Design Engineers: Burkes Green

Main Contractor: Clare Civil Engineering

Description: The works at Phase 6, Dublin Airport involved the installation of AGL lighting, High mast lighting, taxi way guidance signage, FLYCY cabling installations, Constant Current Regulators, primary & secondary cabling & terminations, and transformer installations. Also, included in the installation was the complete electrical fit out of a new sub station building including MV switch gear, LV Distribution boards, and LV services including lighting, fire detection, fire suppression systems, general services, and small power.